Sunday, December 21, 2008

Developers push for wind farm rules


TIMES STAFF WRITER

Friday, December 5, 2008

BP asks the JCIDA to hurry uniform wind PILOTs

  BP Cape Vincent Wind Farm developer asked for speed from the Jefferson County Industrial Development Agency on creating a uniform tax-exempt policy.



By NANCY MADSEN
TIMES STAFF WRITER
FRIDAY, DECEMBER 5, 2008

A local wind power developer asked for speed from the Jefferson County Industrial Development Agency on creating a uniform tax-exempt policy.

"The need for a uniform policy is great," said BP Alternative Energy representative John S. Harris, attorney with McKenna Long and Aldridge, Albany. "It certainly allows BP to make a business decision to move forward. We are willing to engage in dialogue on what makes sense."

Link here to continue reading

Saturday, November 1, 2008

Panel seeking specifics on noise


"I think if we knew ambient and could come up with an average, that would give us something to work with," said Beth A. White, president of Voters for Wind.

TIMES STAFF WRITER

CAPE VINCENT — Members of the committee formed to produce a zoning amendment to deal with wind farms want specifics.
During a meeting Thursday afternoon, the committee agreed to ask the acoustical engineering firm Cavanaugh Tocci Associates, Sudbury, Mass., to evaluate the noise-measuring methods in different laws. That firm panned Hessler Associates' ambient noise study in BP Alternative Energy's draft environmental impact statement for the Cape Vincent Wind Farm.

Saturday, September 27, 2008

Boundaries agreed to for Cape wind turbines


TIMES STAFF WRITER

Thursday, August 21, 2008

Cape's proposed wind law unveiled

The law would allow noise up to six decibels above ambient sound level at neighbor's residences and 10 decibels above ambient sound level at a neighbor's property lines.


TIMES STAFF WRITER

Thursday, July 31, 2008

BP ~ Open house on Cape Vincent wind project

Updated 07/31/2008 06:28 AM

CAPE VINCENT, N.Y. -- Various people with various opinions, all wishing to find out more information and ask questions about the 142-megawatt, 95-turbine wind project planned for the agricultural areas of Cape Vincent. BP Alternative Energy held an open house Wednesday to inform people of the potential project. The company detailed where they would build roads, place transmission lines and most importantly, put up turbines.
"We want to make sure that people don't get misconceptions about our project and that we're able to address specific details. There are a lot of concerns people have about location, visual impact, sound and environmental studies," BP Alternative Energy Cape Vincent Project Manager Jim Madden said.

Monday, March 10, 2008

Cape Vincent Wind SDEIS & St. Lawrence Wind FEIS Documents


BP Wind Energy submitted their Draft Environmental Impact Statement for their proposed cape Vincent Wind Complex  in 2008.
  BP Wind energy purchased the rights to Acciona's St. Lawrence Wind farm - february 2012.

Below are links to BP's Draft Environmental Impact Statement (DEIS) and Acciona's Final Environmental Impact Statement (FEIS)




BP SDEIS ~ Cape Vincent "Wind Farm" Document  Collection 




Acciona's St. Lawrence "Wind Farm" FEIS Document Collection 



Friday, February 29, 2008

February 2008 ~ NYS DEC Comments Re: BP's Draft Environmental Impact Statement

 Alexander B. Grannis
Commissioner DEC

February 29, 2008

Mr. Richard Edsall, Chairman
Town of Cape Vincent Planning Board
1964 NYS Route 12 E
PO Box 680
Cape Vincent, New York 13618

Re: State Environmental Quality Review (SEQR)
Cape Vincent Wind Power Project
BP Alternative Energy
Towns of Cape Vincent and Lyme, Jefferson County

Dear Mr. Edsall:

The New York State Department of Environmental Conservation (DEC) has reviewed the Draft Environmental Impact Statement (DEIS) for the proposed Cape Vincent Wind Power Project, Towns of Cape Vincent & Lyme, Jefferson County, New York, December 7, 2007, prepared by Environmental Resources Management (ERM). The project sponsor, BP Alternative Energy, proposes construction and operation of an approximately 210 megawatt (MW) wind power project consisting of up to 140 wind turbines with a nameplate capacity of 1.5 MW to 2.5 MW, construction of approximately 18 miles of gravel access roads, installation of 18 miles of electric collection line, construction of an operations & maintenance (O&M) center on a 5-acre site, construction of a collection substation on a 3-acre site, and a 115kV transmission line to the existing electrical substation in the Town of Lyme. The project includes 2-3 meteorological (met) towers to be spaced across the project area, and temporary ancillary construction facilities, including two concrete batch plants, and cleared areas for equipment laydown, construction parking and construction management trailers.
DEC’s review of the DEIS has found serious deficiencies in terms of the proposed project scope, location of proposed project components, characterization of natural resources in the project development area, assessment of potential environmental impacts, and discussion of mitigation options. Additionally, the intention to defer, completion of the proposed project layout, basic resource studies and other developmental plans until the final environmental impact statement (FEIS), or later, limits meaningful review and comment on the proposed action by involved agencies and the public, it does not allow for a full public discussion of reasonable alternatives review of the DEIS shows that at least 21 plans, studies or reports necessary to adequately assess the potential environmental impacts of the project have been deferred to the FEIS or later. Several of these are important for DEC's consideration of permit applications that are anticipated to be required for construction of the project. These include a detailed map of the turbine   array and projects components, turbine specifications, wetland delineations, transportation study and routing plan, final visual analysis, archaeology and architectural surveys, Indiana bat survey, Blandings turtle trapping study, storm water and erosion control plans, including a survey of karst features, and it environmental monitoring plan. Further, the DEIS does not anticipate that a number of items recommended by the DEC in comments on the draft public scoping document will be discussed even in the FEIS, including source location(s) for aggregate materials, environmental restoration plan, and operations and maintenance plan,  a compensatory wetland mitigation plan, and invasive species control plan, or a plan for offsets to impacts to  visual and historic resources.
DEC strongly recommends that a supplemental DEIS (SDEIS) be prepared to include more complete data pertaining to these resources, in order that involved agencies and the public have the opportunity to comment on potential impacts to these resources. As an involved agency under the state environmental quality review (SEQR),DEC must make findings based on the record in the FEIS prior to approval of any agency permits that may be required for project construction. A complete EIS record is critical to the DC, and without it the department will have a limited ability to make the required findings as an involved agency.

DEC provided comments on the DEIS Draft Scoping Document, dated August 13, 2007 in a letter to the planning board dated September 14, 2007. The draft scoping document proposed the EIS process " will take place in two phases. In the first phase, wider core doors of potential impact throughout the project will be studied" and" will be presented in the draft EIS." Then, following a" more detailed turbine plan which will specify the final placement of turbans, roads, a substation, electrical interconnects, transmission line, and a permanent maintenance facility… A revised draft EIS will be prepared…"  (draft scoping document, page 2). In comments on the draft scoping document, DEC stated that," SEQR regulations at 617.9(a)(7) provided existing process for the lead agency to require a supplemental EIS, subject to the full set of procedural requirements for the DEIS" in order to ensure that all phases of the DEIS process allow for ample review by involved agencies and the public,DEC further recommended that"… A formal scoping process be conducted again prior to preparation of a SDEIS, in order that the full range of issues of concern to involved and interested parties can be addressed." DEC is disappointed that the final public scoping document, dated October 8, 2007, fails to include the  “revised" DEIS, and defaults to a schedule that defers a full discussion of project details and potential impacts to the FEIS.