Saturday, November 1, 2008

Panel seeking specifics on noise


"I think if we knew ambient and could come up with an average, that would give us something to work with," said Beth A. White, president of Voters for Wind.

TIMES STAFF WRITER

CAPE VINCENT — Members of the committee formed to produce a zoning amendment to deal with wind farms want specifics.
During a meeting Thursday afternoon, the committee agreed to ask the acoustical engineering firm Cavanaugh Tocci Associates, Sudbury, Mass., to evaluate the noise-measuring methods in different laws. That firm panned Hessler Associates' ambient noise study in BP Alternative Energy's draft environmental impact statement for the Cape Vincent Wind Farm.

Saturday, September 27, 2008

Boundaries agreed to for Cape wind turbines


TIMES STAFF WRITER

Thursday, August 21, 2008

Cape's proposed wind law unveiled

The law would allow noise up to six decibels above ambient sound level at neighbor's residences and 10 decibels above ambient sound level at a neighbor's property lines.


TIMES STAFF WRITER

Thursday, July 31, 2008

BP ~ Open house on Cape Vincent wind project

Updated 07/31/2008 06:28 AM

CAPE VINCENT, N.Y. -- Various people with various opinions, all wishing to find out more information and ask questions about the 142-megawatt, 95-turbine wind project planned for the agricultural areas of Cape Vincent. BP Alternative Energy held an open house Wednesday to inform people of the potential project. The company detailed where they would build roads, place transmission lines and most importantly, put up turbines.
"We want to make sure that people don't get misconceptions about our project and that we're able to address specific details. There are a lot of concerns people have about location, visual impact, sound and environmental studies," BP Alternative Energy Cape Vincent Project Manager Jim Madden said.

Monday, March 10, 2008

Cape Vincent Wind SDEIS & St. Lawrence Wind FEIS Documents


BP Wind Energy submitted their Draft Environmental Impact Statement for their proposed cape Vincent Wind Complex  in 2008.
  BP Wind energy purchased the rights to Acciona's St. Lawrence Wind farm - february 2012.

Below are links to BP's Draft Environmental Impact Statement (DEIS) and Acciona's Final Environmental Impact Statement (FEIS)




BP SDEIS ~ Cape Vincent "Wind Farm" Document  Collection 




Acciona's St. Lawrence "Wind Farm" FEIS Document Collection 



Friday, February 29, 2008

February 2008 ~ NYS DEC Comments Re: BP's Draft Environmental Impact Statement

 Alexander B. Grannis
Commissioner DEC

February 29, 2008

Mr. Richard Edsall, Chairman
Town of Cape Vincent Planning Board
1964 NYS Route 12 E
PO Box 680
Cape Vincent, New York 13618

Re: State Environmental Quality Review (SEQR)
Cape Vincent Wind Power Project
BP Alternative Energy
Towns of Cape Vincent and Lyme, Jefferson County

Dear Mr. Edsall:

The New York State Department of Environmental Conservation (DEC) has reviewed the Draft Environmental Impact Statement (DEIS) for the proposed Cape Vincent Wind Power Project, Towns of Cape Vincent & Lyme, Jefferson County, New York, December 7, 2007, prepared by Environmental Resources Management (ERM). The project sponsor, BP Alternative Energy, proposes construction and operation of an approximately 210 megawatt (MW) wind power project consisting of up to 140 wind turbines with a nameplate capacity of 1.5 MW to 2.5 MW, construction of approximately 18 miles of gravel access roads, installation of 18 miles of electric collection line, construction of an operations & maintenance (O&M) center on a 5-acre site, construction of a collection substation on a 3-acre site, and a 115kV transmission line to the existing electrical substation in the Town of Lyme. The project includes 2-3 meteorological (met) towers to be spaced across the project area, and temporary ancillary construction facilities, including two concrete batch plants, and cleared areas for equipment laydown, construction parking and construction management trailers.
DEC’s review of the DEIS has found serious deficiencies in terms of the proposed project scope, location of proposed project components, characterization of natural resources in the project development area, assessment of potential environmental impacts, and discussion of mitigation options. Additionally, the intention to defer, completion of the proposed project layout, basic resource studies and other developmental plans until the final environmental impact statement (FEIS), or later, limits meaningful review and comment on the proposed action by involved agencies and the public, it does not allow for a full public discussion of reasonable alternatives review of the DEIS shows that at least 21 plans, studies or reports necessary to adequately assess the potential environmental impacts of the project have been deferred to the FEIS or later. Several of these are important for DEC's consideration of permit applications that are anticipated to be required for construction of the project. These include a detailed map of the turbine   array and projects components, turbine specifications, wetland delineations, transportation study and routing plan, final visual analysis, archaeology and architectural surveys, Indiana bat survey, Blandings turtle trapping study, storm water and erosion control plans, including a survey of karst features, and it environmental monitoring plan. Further, the DEIS does not anticipate that a number of items recommended by the DEC in comments on the draft public scoping document will be discussed even in the FEIS, including source location(s) for aggregate materials, environmental restoration plan, and operations and maintenance plan,  a compensatory wetland mitigation plan, and invasive species control plan, or a plan for offsets to impacts to  visual and historic resources.
DEC strongly recommends that a supplemental DEIS (SDEIS) be prepared to include more complete data pertaining to these resources, in order that involved agencies and the public have the opportunity to comment on potential impacts to these resources. As an involved agency under the state environmental quality review (SEQR),DEC must make findings based on the record in the FEIS prior to approval of any agency permits that may be required for project construction. A complete EIS record is critical to the DC, and without it the department will have a limited ability to make the required findings as an involved agency.

DEC provided comments on the DEIS Draft Scoping Document, dated August 13, 2007 in a letter to the planning board dated September 14, 2007. The draft scoping document proposed the EIS process " will take place in two phases. In the first phase, wider core doors of potential impact throughout the project will be studied" and" will be presented in the draft EIS." Then, following a" more detailed turbine plan which will specify the final placement of turbans, roads, a substation, electrical interconnects, transmission line, and a permanent maintenance facility… A revised draft EIS will be prepared…"  (draft scoping document, page 2). In comments on the draft scoping document, DEC stated that," SEQR regulations at 617.9(a)(7) provided existing process for the lead agency to require a supplemental EIS, subject to the full set of procedural requirements for the DEIS" in order to ensure that all phases of the DEIS process allow for ample review by involved agencies and the public,DEC further recommended that"… A formal scoping process be conducted again prior to preparation of a SDEIS, in order that the full range of issues of concern to involved and interested parties can be addressed." DEC is disappointed that the final public scoping document, dated October 8, 2007, fails to include the  “revised" DEIS, and defaults to a schedule that defers a full discussion of project details and potential impacts to the FEIS.

Thursday, November 15, 2007

DEC responds to Lymes lead agency request

November 15, 2007: NYSDEC Commissioner Grannis wrote to the Towns of Lyme and Cape Vincent regarding his decision on Lyme’s lead-agency dispute over BP Project. Cape Planning Board claimed lead-agency status within the Town of Lyme because Lyme PB did not respond within 30 days to Cape’s request for lead-agency status. Grannis rejects Lyme’s plea to have lead-agency authority over that portion of the BP Cape-Lyme project within its bounds. It remains to be understood, however, whether Commissioner Grannis was aware of Edsall’s financial ties to BP and the potential conflicts of two other members of the Cape Planning Board. Moreover, if he had been known about these conflicts, would this have changed his findings in this dispute

Sunday, October 14, 2007

VOTERS FOR WIND BACKS PROJECT IN CAPE VINCENT

A new citizens group that supports wind power made its public debut Saturday at an open house for the Cape Vincent Wind Farm.

Voters for Wind has been meeting quietly in Three Mile Bay since June, according to Chairwoman Beth A. White.



Watertown Daily Times (NY)
October 14, 2007

Author: KELLY VADNEY
TIMES STAFF WRITER
Edition: Both
Section: Jefferson
Page: B5
Dateline: CHAUMONT

A new citizens group that supports wind power made its public debut Saturday at an open house for the Cape Vincent Wind Farm.
Voters for Wind has been meeting quietly in Three Mile Bay since June, according to Chairwoman Beth A. White. There are about 20 people in the group, she said.
"We thought this open house was a perfect forum for us to start promoting our group," Mrs. White said.
The group's mission is to promote the Cape Vincent Wind Farm. While Voters for Wind is concerned only with the proposal put forward by BP Alternative Energy, it may one day expand its mission statement to include supporting other wind farms, Mrs. White said.
There are three wind farm proposals in Jefferson County. The St. Lawrence Wind Farm and Cape Vincent Wind Farm are both in Cape Vincent. Horse Creek Wind Farm would cross town lines between Clayton and Orleans.[ Continue via the Watertown Times archives]

Protesters turn out at Cape Vincent wind farm open house

 14 October 2007 The Cape Vincent Wind Farm’s open house Saturday was as much a forum for protest as it was a pursuit of information.


 From the
 Watertown Daily Times (NY) Archives
October 14, 2007
 Protesters Turn out at Cape Vincent W
Author: KELLY VADNEY
TIMES STAFF WRITER
Edition: Both
Section: Jefferson
Page: B5
Dateline: CHAUMONT


Dozens of residents attended the open house put on by BP Alternative Energy, the company that has proposed the wind farm. Many attendees used the event not only to glean information, but to express their opinions about wind power.

Inside the Chaumont fire hall, Voters for Wind, a citizens group that promotes the Cape Vincent Wind Farm, held a bake sale and handed out pro-wind-farm signs and refrigerator magnets.

 [Continue reading via the WDT archives]

Friday, October 12, 2007

CAPE VINCENT DEBATES WIND TURBINE ZONING

Published: October 12, 2007
CAPE VINCENT DEBATES WIND TURBINE ZONING
RENEWED EFFORT: TOWN COUNCIL SAYS IT HOPES TO DRAFT NEW REGULATION PLAN BY EARLY NEXT YEAR
By KELLY VADNEY
TIMES STAFF WRITER
CAPE VINCENT -- The Town Council has agreed to renew its efforts to adopt zoning regulations for wind turbines, but exactly how they would be enacted is a source of bitter debate.

Both Wind Power Ethics Group Chairman Urban C. Hirschey and former Town Councilman Clifford P. Schneider urged the council Wednesday to adopt zoning for turbines.

 [Continue reading Via the WDT archives]