Monday, September 17, 2012

BP's Project Status QUO, in the QUEUE


Posted 9/17/12
9:30PM
Updated 9/18/2012
9:48 AM
The New York Independent System Operator (NYISO) manages New York’s electricity transmission grid – a 10,775-mile network of high-voltage lines that carry electricity throughout the state. The NYISO also oversees wholesale electricity markets where more than $50 billion has been transacted since 1999.

The NYISO Interconnection Queue (the spreadsheet) lists projects that are active in the NYISO interconnection process, or were active in the process but recently went into service (projects that have gone in-service eventually are removed from this list). This list is the “Queue.”

What does British Petroleum’s  buyout of Acciona’s interests in the St. Lawrence Wind development,  mean as far as the positions of the two projects in the NYISO Queue?

When these two projects merged, British Petroleum’s Cape Vincent wind project’s position was # 207 in the Queue. They are planning to connect to the yet to be built RockLedge substation.
In addition, St. Lawrence wind was # 166 in the Queue,the plan for this project is to connect to the existing Lyme Substation.

Last February, I had an opportunity to ask a representative from NYISO how this merger may affect their status in the Queue.

Below are my questions and the answers.

Q1. What happens if a developer sells their project; does the new owner of the project retain its spot in the queue? If not, does the new owner slip back to the last spot in the Queue?

Answer: Under Attachment X of the NYISO Open Access Transmission Tariff (OATT), if a Developer of a project in the NYISO Interconnection Queue sells the project to another Developer, the new Developer assumes “ownership” of the project in its current Queue Position, provided that the new Developer does not modify the project in a way that may affect its Queue Position.

Q2. What happens if a new owner of a project wants to amend the project, e.g. increase or reduce the number of turbines? If they change, do they lose their spot in the Queue?

Answer: Under Attachment X of the OATT, certain modifications to a project may be made without affecting the project’s Queue Position, and certain modifications would cause the project to lose its Queue Position.

Q3. In the case of the St. Lawrence Wind Project being sold to the Cape Vincent Wind Project, both located in the Town of Cape Vincent, Jefferson County, if both project are combined what will be the new status of the combine project in the NYISO Queue.

Answer: Although the two projects may be “combined” outside the NYISO interconnection process, within the NYISO interconnection process the projects will continue to be treated as separate projects in their respective Queue Positions.

Q4. Acciona’s St. Lawrence wind planned to connect to the existing Lyme substation, BP’s Cape Vincent wind is scheduled to connect to the Rockledge substation, that has not been built yet ,if the two projects combine will this change their interconnect point?

Answer: Per the previous answer, the two projects will continue to be treated as separate projects in the NYISO interconnection process. They cannot be “combined” within the NYISO process.

Additionally,
Under the NYISO tariff, a Developer can withdraw their project from the Queue at any time (they don’t have to give a reason).
The tariff also allows NYISO to withdraw a project from the Queue for very specific reasons/circumstances spelled out in the tariff. (NYISO cannot withdraw a project from the Queue without a reason defined in the tariff.)

NOTE
At this point in time, British Petroleum’s Cape Vincent wind and Acciona's St. Lawrence wind projects, have merged and continue to retain their positions and remain active in the interconnect Queue.  Year to date thirty two projects have withdrawn from the QUEUE . I do not know if this affects BP's position in the QUEUE.

Below is the portion of the QUEUE spreadsheet that pertains to Cape Vincent




Link here to the complete NYISO Queue spreadsheet updated August 31/2012


APPLICATION BY NIAGARA MOHAWK POWER CORPORATIONTO INSTALL A 115kV GENERATOR ATTACHMENT FACILITYAND PERFORM MISCELLANEOUS FACILITIES WORK TO ACCOMMODATE THECONSTRUCTION OF THE CAPE VINCENT WIND FARM GENERATION FACILITIES (ROCKLEDGE)


BP ~ Cape Vincent Wind Farm Application Documents ~No Downloading Required

1.
BP ~ Application to Site , Wind Electric Generating Facility in the Town of Cape Vincent, New York.
September 17, 2012

2.
BP ~ Application to site Wind Electric Generating Facility in the Town of Cape Vincent, New York. Exhibit A

3.
BP ~ Application to site Wind Electric Generating Facility in the Town of Cape Vincent, New York. Exhibit B

4.
BP ~ Application  to site Wind Electric Generating Facility in the Town of Cape Vincent, New York. Exhibit C

5.
BP ~ Application  to site Wind Electric Generating Facility in the Town of Cape Vincent, New York. Exhibit D

6.
BP ~ Application  to site Wind Electric Generating Facility in the Town of Cape Vincent, New York. Exhibit E

7.
BP ~Application to site Wind Electric Generating Facility in the Town of Cape Vincent, New York. Exhibit F1
(the economic impacts of wind developments)

8.
BP ~ Application to site Wind Electric Generating Facility in the Town of Cape Vincent, New York. Exhibit G 
(News letters Re CV Wind project & Acciona, publication ~ Understanding PILOT Programs)

9.
BP ~Application to site Wind Electric Generating Facility in the Town of Cape Vincent, New York.
Exhibit H 
(WDT Story Re: Projects Merge)

10.
BP ~ Application to site Wind Electric Generating Facility in the Town of Cape Vincent, New York. Exhibit I
 (list of Stake holders)

BP ~ Application ~  to site Wind Electric Generating Facility in the Town of Cape Vincent, New York. ~  PUBLIC INVOLVEMENT PROGRAM

Sunday, September 16, 2012

BP’s Project Developer stays true to form and “engages” our community through the Watertown Times

Posted
9/16/12
8:31 AM
Update:12:28 PM 9/16/12

Today in the Watertown Daily Times there is a full page spread extolling the virtues of BP’s Cape Vincent Wind project

BP’s Project Developer Richard Chandler claims to be “engaged” with our community. His engagement consists of a paid advertisement in the Watertown Daily Times and a letter to our community telling us that our zoning law is overly burdensome and we should follow industry standards. Apparently protecting the health and welfare of the citizens of our community is overly burdensome for BP. Additionally, choosing to do a PR Blitz in a local newspaper rather than “engaging” in a meaningful dialog demonstrates a profound lack of respect for our community…




Additionally this is the same old, tired advertisement BP used Feb 12, 2012  Two days after the announcement in the Watertown Times that BP had purchased the rights to Acciona' St Lawrence Wind farm . For his latest piece of propaganda (above) Chandler copied a couple of paragraphs from his comment letter to the Public Service Commission  Re: article 10 .
~~~~~~~~
Below is a copy of BP's advertisement from the Watertown Times 2/12/12



Wednesday, September 12, 2012

Cape Vincent Planning Board to decide BP’s wind farm proposal

CAPE VINCENT — The town’s Planning Board will consider terminating BP’s wind farm application at its regular board meeting 7 p.m. today in the Recreation Park building on James Street.
ARTICL 
Continue reading via this link

Planning Board Chair addresses the Status of BP's Cape Wind project


Tonight at the Cape Vincent Planning Board Planning Board Chair Richard Macsherry read the following letter that he sent to Mr. Richard Chandler Director of Development BP, Wind Energy North America. Regarding the status of Bp’s Cape Vincent Wind Project

RE: BP Wind Energy Application(s)
Dear Mr. Chandler:
This letter is to remind you that the local law entitled Cape Vincent wind
Moratorium will expire Friday, September 7, 2012. The town of Cape
Vincent(New York) planning board has had no correspondence with your
office from well before the law's enactment, to the date of this letter.

The town of Cape Vincent planning board, as Lead Agency SEQR,
requests that BP Wind Energy North America, Inc. Provide A written update
on the status and plans for ward for all current and proposed alternative
energy project, applications specific to this Township. You are asked to
ensure that the requested update is received by the town supervisor's office
no later than Wednesday, October 3, 2012.

Please be advised that in the event that this request is not fulfilled, the town
of Cape Vincent Planning Board reserves the right to deem current
alternative energy project applications under the auspices of BP Wind
Energy to be incomplete and abandoned.

BP Wind Energy Application(s)
September 6, 2012
page 2.
Thank you in anticipation of BP Wind Energy' s prompt response.
Richard H. MacSherry, Chair
Town of Cape Vincent Planning Board
Cc: town board, planning board, M. Gebo, Esq., P. Curtain Jr., Esq.





Sunday, September 9, 2012

Do ya, feel lucky? Well, do ya, punk?

    BP wind energy's project Director of Development Richard Chandler  sent a letter to the Town of Cape Vincent June 27, 2012 concerning Cape Vincent proposed zoning law.

 Chandler wrote that BP has been “engaged” with the Town and members of its community for many years.The town has already evaluated potential impacts from the Cape Vincent and St. Lawrence Wind Farm projects and made favorable findings. Under Board members with conflicts of interest that signed loyalty clauses.

 At this point BP has two choices as to how they can proceed.
They can continue to "work closely” with our community, implementing their plan of attack until they feel they have sufficiently neutralized the opposition, or until they feel they have exhausted all other options and then proceed under article 10.
It all depends how lucky they feel.
 Once they go to an article 10 process the fate of their project is out of their hands and there is no turning back …


Below is a reproduction of  Chandler's letter .


June 27, 2012

Via Electronic Delivery


Town of Cape Vincent
P. O. Box 680
Cape Vincent, N Y 13618
Re: Proposed Amendment – 2012 of Town Of Cape Vincent Zoning Law

On June 5, 2012 the town of Cape Vincent (“ Town") issued Proposed Amendment – 2012 to the
Town of Cape Vincent Zoning Law (" Proposed Zoning Law"). The Proposed Zoning Law would
effectively prohibit wind generation from being sited within the Town. The town has already
evaluated potential impacts from the Cape Vincent and St. Lawrence Wind Farm projects and
made favorable findings. The requirements of the Proposed Zoning Law, however, are
inconsistent with these findings. The requirements, setback provisions, exclusion areas, and noise
standards contained within the Proposed Zoning Law are highly restrictive and should be
substantiated by realistic and credible studies, consistent with other operational wind projects, and
in line with industry standards.

As you know, the developers of the Cape Vincent Wind Farm and St. Lawrence Wind Farm
Projects (combined" the project") have been engaged with the Town and members of its
community for many years. By working closely with the community, BP has been able to make
several changes to and positively shape the Project into one that will provide significant benefits
to the Town and the community and do so in an environmentally responsible manner. Wind
development in the Town will create jobs, increase the demand for local goods and services, and
increase tax revenues to the Town, County, and school district. Land owners will be able to
secure an additional revenue stream while continuing to use their property for agricultural and
recreational uses, a positive benefit during challenging economic times. The Project also will
provide renewable power that is good for the environment.

For parties interested in submitting applications to site wind energy projects in the Town of Cape
Vincent, the provisions contained within the Proposed Zoning Law are unreasonably burdensome
that's in view of existing wind generation technology and/or in view of the needs of/costs to
ratepayers. We respectfully request the town to reconsider the Proposed Zoning Law, taking into
account the above mentioned comments.



~~~~~~~~~~~~~~~




Below are excerpts  from wind leases signed by conflicted board members that may  explain the favorable findings for the development of BP's project that Chandler mentions in his letter.

click here to view BP Wind Lease agreement
click here to view BP Wind  Good Neighbor agreement
click here to view Acciona Wind  lease agreement
~~~~~~~~~~~~~~

Below are the loyalty clauses from BP's & Acciona's wind leases



Thursday, September 6, 2012

Cape Vincent Wind Moratorium

Expires Friday, September 7, 2012


The moratorium  the town board enacted honored the request of a petition submitted to the Town Board June of 2009 ,signed by almost 800 people asking for a one year moratorium . The intention was to allow the town to update their Comprehensive plan and zoning law and to regulate wind development for the well being and safety of the community.  Both of these goals have been accomplished





Notice of moratorium.




Article 1. – Statement of Authority.

The town for the town of Cape Vincent, pursuant to the authority granted it under article 60 of the law and sections 10 and 20 of the municipal law of the state of New York, hereby enact as follows:

Article 2. – Statement of Purpose and Findings.

The town board of the town of Cape Vincent has been made aware of interests in wind power generating facilities desiring to locate in the town of Cape Vincent. At the same time, the town board is aware that their are many concerns and questions about the establishment of wind power in generating facilities being located in the town. Currently, the town of Cape Vincent code does not contain provisions for regulation of such facilities. It is the purpose of this local law to enact a moratorium work. Through September 7, 2012 for applications or proceedings of applications for wind power generating facilities to allow the town board to consider and implement sufficient regulations that address the development and maintenance of wind power generating facilities.

Article 3. – Enactment.
The town board the town of Cape Vincent does hereby enact as follows:

Section 1. Definitions.

When generating facilities: those facilities which generate original power to be used on-site or to be transferred to the transmission system for distribution to customers or third party utility companies. The definition of wind power generating facility shall include individual wind power generating facilities, directed and used for private use. It shall also include accessory facilities such as transmission lines, access roads, meteorological towers and other related facilities, whether the primary when generating facilities are located within or outside of the town of Cape Vincent.

Section 2.
Commencing with the effective date of this local law and for the. Through September 7, 2012, no person shall be allowed to permit or site or locate a wind power generating facility is defined in this law within the town of Cape Vincent.

Article 4. – Severability.

If any part of this chapter shall be found to be void, voidable, or unenforceable for any reason whatsoever, it shall not affect the validity or enforceability of any remaining section or provisions of this chapter.

Article 5. – Effective date.

This local law shall take effect immediately upon filing with the Secretary of State.


Link here to read the 82 page petition calling for a wind development moratorium

Monday, September 3, 2012

Pimping Wind ~ BP" Style of Community Outreach ~

  Last year around this time, just before the Republican Primary a “Clean Energy” educational forum presented by the New York Wind Education Collaborative, a conglomeration of the Alliance for Clean Energy New York (ACE), Albany and Citizens Campaign for the Environment, the CCCE is an offshoot coalition derived from Marion Trieste’s public education campaign.

Carol E. Murphy, executive director for the Alliance for Clean Energy New York, Albany was quoted in the Watertown times describing the mission of their “educational” forum.

“We came to offer the latest scientific information to people — it’s all out there for people to look at,” “but people won’t believe it if they don’t want to believe it.”

The collaboratives stated goal was to increase the public’s understanding of wind power issues, in the belief that a better-informed public can participate more meaningfully in the environmental review process and other public discussions surrounding proposed wind facilities.

Among other things, the Forum provided an “independent expert " who defended a study supporting the notion that Wind Turbines do not impact property values.
The statement was made by their expert that the review of Cape Vincent’s economic report Re: Wind development impacts by McCann Appraisal, LLC was laughable.

What is laughable is that they would have us believe that their educational forum was independent and unbiased.
~~~
August 26, 2011, I submitted a FOIL request to the Town Clerk of the Town of Cape Vincent for the following.
A copy of the correspondence and transaction information concerning the forum scheduled to be presented at Rec. Park August 30, 2011.
I received a letter in response telling me that the Rec Park facility had been rented by BP

Below is a copy of that letter






Sunday, September 2, 2012

BP's Project Developer ~ Richard Chandler's TOP SECRET Development Strategy

BP’s  project manager Richard Chandler  submitted a comment letter to the Public Service Commission informing them that BP Wind Energy is seeking an Article 10 process that will facilitate its development and construction of their Cape Vincent Wind project.
At this point BP’s actions are unpredictable, will they ignore Cape Vincent’s new zoning regulations and seek an article 10 process? Or will they challenge our revised zoning law?


Lady Grace  recently discovered Richard Chandler's  Top Secret  development strategy for BP's Cape Vincent Wind Farm

Saturday, September 1, 2012

IS BP ANTI - MILITARY?




I found an interesting paragraph in BP's SDEIS . Their rational as to why their project would be good for our community.

BP’s SDEIS

2.10.1.2 Permanent Impacts

Jefferson County is currently experiencing substantial growth in human population and housing developments, as evidenced by population and housing growth estimates in Fort Drum, where the number of soldiers, spouses, and other personnel moving to the Fort Drum area is projected to increase by nearly18,000 people between 2004 and 2013.
To accommodate this population growth, the Department of Defense estimated in 2005 that an additional 2,000 homes would need to be built off of the Fort Drum base over the coming years.

Due to these and other development pressures, in the event that the Project is not constructed, the current population and development growth trends will probably result in the loss of current and traditional land uses for the area. This would result in fewer undeveloped open spaces and lower human density conditions. The Project, once constructed, will likely preclude additional housing developments and will result in less fragmented conditions when compared to future scenarios without the development of the Project.

My interpretation of what they are saying


Our project is good because if developed it will preclude military families from building homes in Cape Vincent , thus preventing the fragmentation and loss of farmland as well as preventing lowered living conditions caused by an increase in population.


This is absolutely unbelievable!


Link to SDEIS