The NY Dept. of Public Service’s sent a very pointed letter to the PB and Edsall about the inadequacy of St. Lawrence Wind Power’s DEIS. Comments include the fact the PB as lead agency basically ignored the requests of the NYDPS to do an adequate job on numerous areas of concern provided previously by the NYDPS. They tell the PB they should start the process over, and get qualified help to do these studies correctly. They indicate this study should never have been accepted by Edsall and the planning board. It is proof by a major involved NY agency of the rushed nature of the town and its planning board. As with the NYDEC the DPS had no way of knowing of the conflicts of interest of three PB members now acting as lead agency because there were still no official conflict disclosures by conflicted town officers.
Wednesday, June 13, 2007
Tuesday, June 12, 2007
Voter For Wind~ Dawn Munks Testimonial letter written to Geos Global
Bp, hired Marion Trieste ,managing director of Geo’s Global, to help facilitate their Cape Vincent Wind Farm Project . Trieste helped launch Voters For Wind as a vehicle to promote BP's project .
Dawn Munks Testimonial letter written to Geos Global
Link here to read petition and Resolution
Dawn Munks Testimonial letter written to Geos Global
Link here to read petition and Resolution
Wednesday, March 14, 2007
Lyme May Want Own Study of Wind farm
Link not available
By Kelly Vadney
Watertown Daily Times
03/14/2007
The immediate future of BP Alternative Energy’s proposed Cape Vincent Wind Farm may hinge on what transpires at the Lyme Town Council’s meeting today.
The issue is whether Cape Vincent will supervise the entire environmental review for the proposed 210-megawatt wind farm project, which crosses town lines, or if the Lyme Town Council will opt for a separate environmental review for the portion in Lyme. That could slow development of the wind farm.
[Continue via the WDT archives]
Friday, February 23, 2007
Lyme wants Brakes on Wind farm Project
Link not available
By Kelly Vadney
Watertown Daily Times
Date: 02/23/2007
Based on comments at a Thursday wind power meeting, Lyme residents are keeping an open mind about a proposed wind farm, but they would like to slow the process down and have their own say.
“My perspective is, things are moving too fast and we need to slow down,” Councilman Warren A. Johnson said. “I think my fellow councilmen agree with that.”
[Continue via the WDT archives]
Tuesday, February 13, 2007
WIND POWER: ETHICS GROUP, DEC DECRY ACCEPTANCE OF UNFINISHED REPORT
February 13, 2007
WIND POWER: ETHICS GROUP, DEC DECRY ACCEPTANCE OF UNFINISHED REPORT TURBINE STUDIES CAUSE A STIR
Author: KELLY VADNEY TIMES STAFF WRITER Edition:
Both Section: Jefferson
Page:B1
Dateline: CAPE VINCENT Estimated printed pages: 3 Article Text: The Wind Power Ethics Group and the state Department of Environmental Conservation say the town Planning Board should not have accepted a draft environmental impact statement for the St. Lawrence Wind Farm.
Judy Drabicki, a Dexter attorney representing the ethics group, a citizens' organization that has opposed wind farm development, said the developer has not sufficiently identified impacts because studies listed as part of the review have not been completed, including those for wetlands.
Continue via the WDT archives
WIND POWER: ETHICS GROUP, DEC DECRY ACCEPTANCE OF UNFINISHED REPORT TURBINE STUDIES CAUSE A STIR
Author: KELLY VADNEY TIMES STAFF WRITER Edition:
Both Section: Jefferson
Page:B1
Dateline: CAPE VINCENT Estimated printed pages: 3 Article Text: The Wind Power Ethics Group and the state Department of Environmental Conservation say the town Planning Board should not have accepted a draft environmental impact statement for the St. Lawrence Wind Farm.
Judy Drabicki, a Dexter attorney representing the ethics group, a citizens' organization that has opposed wind farm development, said the developer has not sufficiently identified impacts because studies listed as part of the review have not been completed, including those for wetlands.
Continue via the WDT archives
Thursday, January 11, 2007
2007 ~ BP Escrow account Details
At the January 11, 2007:Town Board meeting Supervisor Rienbeck asked for permission to sign the agreement with the BP Wind tower group regarding their Escrow Account. No resolution to authorize the escrow account, just permission...
~~~~~~
Minutes From Town Board Meeting January 11,2007

British Petroleum Escrow Account Document Page 1

British Petroleum Escrow Account Document Page2

British Petroleum Escrow Account Document Page3

British Petroleum Escrow Account Document Page4

British Petroleum Escrow Account Document Page5

British Petroleum Escrow Account Document Page6
~~~~~~
Minutes From Town Board Meeting January 11,2007

British Petroleum Escrow Account Document Page 1

British Petroleum Escrow Account Document Page2

British Petroleum Escrow Account Document Page3

British Petroleum Escrow Account Document Page4

British Petroleum Escrow Account Document Page5

British Petroleum Escrow Account Document Page6
Subscribe to:
Posts (Atom)