Thursday, November 15, 2007

DEC responds to Lymes lead agency request

November 15, 2007: NYSDEC Commissioner Grannis wrote to the Towns of Lyme and Cape Vincent regarding his decision on Lyme’s lead-agency dispute over BP Project. Cape Planning Board claimed lead-agency status within the Town of Lyme because Lyme PB did not respond within 30 days to Cape’s request for lead-agency status. Grannis rejects Lyme’s plea to have lead-agency authority over that portion of the BP Cape-Lyme project within its bounds. It remains to be understood, however, whether Commissioner Grannis was aware of Edsall’s financial ties to BP and the potential conflicts of two other members of the Cape Planning Board. Moreover, if he had been known about these conflicts, would this have changed his findings in this dispute